We are excited to share with you this week’s factory update! Our construction team has been working incredibly hard, in order for us to get chocolate in your hands as soon as possible!
Aerial view of the factory on Monday.
Aerial view of the factory Friday.
As you can see from the pictures above, we started framing on Monday and by Friday we were able to get eight rooms framed!
We also finished grading the parking lot this week in preparation for asphalt paving to be completed on February 4.
We sealed and primed steel beams that span the Chef’s Table Kitchen and support the second floor and roof.
The control systems and solar panel inverters for the PV Micro Grid will be enclosed in and sit on the cement pad pictured above which was poured on Friday.
As the walls start to go up, we are beginning to see the breathtaking views that our second floor Ku’ia Pavilion will have! We look forward to welcoming you to the factory later in 2019!